Year: 2020
Location: Beaconsfield, Sydney
Materials: Structural Steel
Project Duration (3D modelling, fabrication & Installation): 4 weeks,
The structure is made from a series of 380 PFCs and 310UC158 beams attached to two concrete columns, and a slab edge creating an additional 140m 2 of floating office space. The concrete columns were scanned to ensure that none of the proposed structural bolts would interfere with the reinforcement and undermine their integrity.